Barton Helipad Groundworks Investigation

Drainage.jpg

We were employed to undertake a full groundworks investigation of the existing drainage within this site. Unfortunately, due to the condition and age of the existing drainage system no records were available to assist our operation.

Further Groundworks Investigation Provides Successful Solution

It was found that the existing system had been laid in a twin trench and was in a substandard condition. Work was carried out to repair the defected lines without effecting the operational function of the helipad, which throughout our contract it was actively being used by both the Air Ambulance and Police force.

The repairs were successfully located and over pumping carried out to maintain the system.

Civil Engineering, Drainage Works